DRAW RELEASE PROTOCOL // AIA G702 LINES 7 & 8

Conditional vs. Unconditional Lien Waivers & The Two-Waiver Rule

Use a Conditional Waiver before funds clear the bank, and an Unconditional Waiver only after funds settle. On commercial projects running monthly progress draws, general contractors and construction lenders pair both waivers in every packet after Draw #1 so current payment is conditioned on delivery while last month's disbursement is proven cleared.

The 4 Types of Construction Lien Waivers

Comparison of the four mechanics lien waiver types
Waiver TypeWhen EffectiveG702 Tie-OutRetainage Covered?
Conditional ProgressUpon bank clearance of current draw check/ACHLine 8 (Current Due)No (carved out through date)
Unconditional ProgressImmediately upon signature (even if unpaid)Line 7 (Prior Paid)No (progress period only)
Conditional FinalUpon bank clearance of final payment + retainageFinal Line 8 + RetainageYes, once final check clears
Unconditional FinalImmediately upon signature; permanent releaseFull Contract Sum (Line 3)Yes, permanent closeout

How the Two-Waiver Rule Works Across Monthly Draws

Title companies issuing ALTA 32/33 date-down endorsements refuse to rely indefinitely on conditional progress waivers because a conditional waiver proves only that a check was expected, not that it cleared without bouncing. The Two-Waiver Rule closes that audit trail by rolling every conditional waiver into an unconditional waiver on the next billing cycle:

Month-by-month Two-Waiver Rule draw timeline
Draw CycleG702 Line 7 (Prior Paid)G702 Line 8 (Current Due)Required Waivers in Packet
Draw #1 (Oct 31)$0.00$120,000.00Conditional Progress Waiver for $120,000.00 through Oct 31.
Draw #2 (Nov 30)$120,000.00$150,000.00(1) Prior Unconditional Progress Waiver for $120,000.00 through Oct 31 + (2) Current Conditional Progress Waiver for $150,000.00 through Nov 30.
Draw #3 (Dec 31)$270,000.00$142,850.00(1) Prior Unconditional Progress Waiver covering $270,000.00 cumulative (or $150,000.00 discrete Draw #2) through Nov 30 + (2) Current Conditional Progress Waiver for $142,850.00 through Dec 31.

Three Traps That Break Waiver Coverage

1. Through-Date vs. Payment-Date Confusion

Statutory forms in California (Civ. Code § 8132), Arizona (A.R.S. § 33-1008), Texas (Prop. Code § 53.284), and Nevada (NRS § 108.2457) measure waiver scope by the Through Date (billing cutoff), not the date the check is cut. Putting a later check date in the Through Date field accidentally waives unbilled work performed after the pay app cutoff.

2. Georgia 90-Day & Mississippi 60-Day Automatic Conversion

Unlike four-form states, Georgia (O.C.G.A. § 44-14-366) and Mississippi (Miss. Code § 85-7-433) use statutory Interim Waivers that convert into binding unconditional releases after 90 days (GA) or 60 days (MS) unless the subcontractor records a statutory Affidavit of Nonpayment before the clock expires.

3. Missing Prior Unconditional on Cumulative Line 7

If a subcontractor bills $270,000 on Line 7 Previous Certificates but only submits a prior unconditional waiver for $120,000, the GC carries a $150,000 gap in cleared-fund proof. Reconcile Line 7 in either Cumulative mode or Discrete Period mode against the prior draw ledger.

Automate Two-Waiver Parity on Every Subcontractor Draw

WaiverAudit reconciles both waivers in one pass: Current Conditional Waiver vs. AIA G702 Line 8 and Invoice Net Due, plus Prior Unconditional Waiver vs. AIA G702 Line 7 (Cumulative or Discrete) across all 12 statutory states and 38 common-law jurisdictions.

Informational compliance guidance only — WaiverAudit is a software verification tool, not a law firm.